Delays mean Leamington park restoration will now be completed in February
But these issues have been resolved at no extra cost and contractors will deliver the project within budget.
The £1.4 million project, which is mainly being funded by Heritage Lottery Grants along with contributions from Warwick District Council and The Friends of the Pump Room Gardens group, is being carried out by two contractors Idverde and Lost Art Limited.
Advertisement
Hide AdAdvertisement
Hide AdIdverde is covering the main landscaping and works with a contract value of £755,000 while Lost Art is restoring the bandstand with a contract value of £254,000.
The work was due to be completed this month but is now more likely to be finished in February.
And the district council’s report, which went before the authority’s overview and scrutiny committee at a meeting on Tuesday evening, said: “The project has had a number of quality issues, mostly dating from the early stages of the project.
“These have been raised at the highest level with Idverde and they have committed to rectifying these issues at no additional cost to the project while demonstrating their commitment to the work.
Advertisement
Hide AdAdvertisement
Hide Ad“The appointment of a clerk of works by Warwick District Council to oversee the works has helped to bring the programme back on track.
“The current position is that the main works are approximately three weeks behind the original programme end date of January 2019.
“Some of these delays have been due to the need to co-ordinate works with Warwickshire County Council over the approach to the central path and the negotiations with Western Power Distribution over problems with the electrical supply.
“The remediation works have not added any significant time delay to the project.”
Advertisement
Hide AdAdvertisement
Hide AdWarwickshire County Council is due to carry out works to improve York Bridge in a separate project due to begin in April . It is expected to take eight weeks to complete.
The bandstand restoration is due to be completed in early February .
This part of the project has also had delays due to the unforeseen need to completely replace the decking.
The forecasted final accounts for both the Lost Art and Idverde projects are within budget, the report says.
The council has said it has become clear that future projects of this type require a dedicated manager from the outset.